Overview

This gadget displays the burnup and/or burndown chart for a project release represented by a Jira issue filter. The calculation can be done by Story Points, Original Time Estimate, Issue Count or by any numerical custom field, relying on historical data for each issue within the specified filter. Additionally, you have the option to include sub-tasks in the calculation. The series to be displayed are configurable, thus allowing you to use the gadget as burndown, burnup or both, providing a flexible tool to monitor the agile progress of your project release.

...

Setting

Description

Gadget title

Choose what to display in the title bar of the gadget.

Data source

Select the type of Data source used by the gadget:

  • ASaved filterthat contains the Jira issues in your release (the scope of your project release). Make sure that the specified filter is shared if you want other people to visualize the dashboard.

  • A JQL query that returns the issues you want to be processed by the gadget.

Time interval

Represents the time interval of the release.

You choose from multiple options:

Custom dates - choose this option if you want to manually enter the Start date and End date of the release.

Dates of a project release - Choose this option if you want the gadget to use the start and end dates of an existing project release (added on the Releases page of a Jira project). Make sure the selected release has a Start date and End date set. Any subsequent changes to the release dates made on the project's Releases page will be automatically reflected in the gadget, without the need to reconfigure it.

Dates of a sprint - Choose this option if you want the gadget to use the start and end dates of an existing sprint. Only the dates are considered (not also the hours). The start of the interval will be the start date of the sprint with time at the start of day, while the end of the interval will be the end date of the sprint with the time at the end of day. When enabled, you’ll need to select the board the sprint belongs to. If you choose the Latest sprint (auto), the date range will automatically match the most recent sprint. If you manually select a specific sprint, any changes made to its dates on the board will be automatically reflected in the gadget, without the need to reconfigure it.

Be aware that you can also check the Continue to display data after release end date option in the More Settings tab if you want the chart to still display data even if the end date has passed.

Intervals of

Indicates the time interval for calculating the chart data. If you do Agile development, this should be set according to the length of your sprints or iterations.

Calculate by

Specify on which criteria the calculation to be performed. You can choose between:

  • Story Points - the default value; use this option if the issues are estimated in Story Points. If the issues are from team-managed projects (aka next-gen projects), select Story Point Estimate instead.

  • Original Time Estimate - use this if you use time estimates; calculation will be done in hours. The Scope will be calculated as the sum of the Original Estimate field of all the issues from the filter, and each time an issue is marked as done, the Burned and Remaining lines will increase/decrease with the amount of hours that is set at Original Estimate for that issue. This option does not consider the time spent (work logged).

  • Time Remaining & Time Spent - use this option if you use time estimates and your team logs the worked time on a daily basis; calculation will be done in hours. The Scope will be calculated as the sum of the Time Spent and Time Remaining of all the issues from the filter. Burned is calculated as the sum of Time Spent of all the issues from the filter plus the sum of Time Remaining of all the issues from the filter that are done. Remaining is calculated as Scope minus Burned. This option does not consider the Original Estimate field.

  • Issue Count - use this if you want the calculation to be done by the number of issues.

  • Other numerical custom fields defined in your Jira instance - pickup the numerical custom field that you use to track or estimate the issues.

...